Supreme Court of India holds that receipt of arbitration notice is the appropriate criterion to determine commencement of arbitral proceedings for the purpose of preserving pre-arbitration interim relief.
The Supreme Court of India, in a judgment dated January 7, 2026, clarified the correct date for commencement of arbitral proceedings under the Arbitration and Conciliation Act, 1996 (“Arbitration Act”). This ruling focused on the 90-day period to maintain pre-arbitration interim relief.
The case was brought by Regenta Hotels Private Limited, a hospitality company, against M/s Hotel Grand Centre Point, a partnership firm, and its partners. In 2019, the parties entered into a Franchise Agreement where Regenta offered brand support and expertise for running a hotel in Srinagar. A conflict arose when one partner allegedly interfered with hotel operations. As a result, Regenta sought an interim injunction from the Trial Court in February 2024, which was granted. Regenta then issued a formal arbitration notice in April 2024, and when the respondent refused to cooperate, it filed a petition for appointing an arbitrator in June 2024. Both the Trial Court and the High Court of Karnataka lifted the interim injunction, stating that arbitral proceedings had not started within 90 days of the interim order, treating the petition filing date as the start date.
The Supreme Court of India confirmed that the commencement of arbitral proceedings is determined solely by when the respondent receives a request to refer the dispute to arbitration. The Court stated that a petition for appointing an arbitrator is just a necessary step due to the respondent’s refusal to engage and cannot replace this date. The Court also clarified that the term “initiated” in the relevant rules should be read in conjunction with “commencement” under the Arbitration Act to ensure the statutory framework remains clear.
Applying these principles to the facts, the Supreme Court ruled that arbitral proceedings began when Regenta sent its arbitration notice in April 2024, which was well within the 90-day period from the February 2024 interim order. The High Court’s focus on the arbitrator appointment petition date was therefore inconsistent with the intent and provisions of the Arbitration Act. Consequently, the Supreme Court allowed the appeal, overturned the High Court’s decision, and reinstated the interim injunction.